Hydraulic Improvements to the High End Level Sewershed Collections System
Trenchless & Tunneling
The scope of work included approximately:
20,100 LF of sewer cleaning and closed circuit television inspection (CCTV)
12,100 LF of replacement of sanitary sewers by opencut method
8,000 LF of new sanitary sewer installation utilizing microtunneling method
200 each of reconnection of sanitary house connections
690 vertical-ft. of replacement of existing sanitary manholes with new sewer manholes
750 vertical-ft. of new manhole installation
Associated wastewater bypass pumping/control of flows of sewer/ manholes to be replaced or constructed and continuous monitoring of the bypass operation
Restoration of pavement, alleys, sidewalks and site restoration